Council has advised residents that the Recycled Water Rising Main construction will progress as follows:
Subscribe now for unlimited access.
$0/
(min cost $0)
or signup to continue reading
Phillip Street between Victoria Street to Dalton Street - 9-12 April
Armstrong Street between Dalton Street to Grenfell Street - 12-15 April
Grenfell Street between Armstrong Street to Close Street - 15-18 April
It is anticipated that construction will cross Dalton Street between 12-13 April, depending on conditions.
Access to Parkes Early Childhood Centre may be temporarily restricted on either Friday 12 or Monday 15 April.
If the car park is closed, parents may use the Parkes Bowling and Sports Club car park on Cecil Street for drop off and pick ups, accessing childcare centre via the gate between car parks.
Please allow extra time for drop off and pick up during the coming week.
PEC staff or anyone needing to leave their vehicles for longer can park in the Little Theatre car park which is accessed via Bogan Street (Newell Highway).
For more information visit: https://www.parkes.nsw.gov.au/?p=5078